The project involves the construction of two lots between Almaty and Khorgos in relation with the West China International Transit Corridor. Within the scope of this critical project; 111,7 km of 2 x 2 lane road is being constructed besides to 44 bridges, overpasses and 7 junctions. The project is financed by the World Bank.
  • Location Almaty / KAZAKHSTAN
  • Client Committee for Roads Ministry of Transport and Communications
  • Total Length of the Lots 111,70 km, 2 x 2 Lane
  • Excavation 287.129 m³
  • Fill 10.025.557 m³
  • Plentmix Subbase 778.947,46 m³ (Lot 1)
    894.435,70 m³ (Lot 2)
  • Base Course 210.119,36 m³ (Lot 1)
    269.582,91 m³ (Lot 2)
  • Bituminous Base Course 29.091,49 m³ (Lot 1)
    19.534,69 m³ (Lot 2)
  • Binder 20.753,46 m³ (Lot 1)
    14.175,68 m³ (Lot 2)
  • Wearing Course 25.942,67 m³ (Lot 1)
    23.550,17 m³ (Lot 2)
  • Concrete 242.550,47 m³ (Lot 1)
    298.868,81 m³ (Lot 2)
  • No. of Bridges and Overpasses 44 (30 No.s Lot 1; 14 No.s Lot 2)
  • No. of Interchanges 7 (3 No.s Lot 1; 4 No.s Lot 2)